// INSTALLATIONS |
|
|
Now let’s look at how a few individual projects were installed by A.C.I |
|
|
EXISTING ROOF: 250,000 square feet 86,000 square feet skylight covered with urethane foam |
|
|
|
|
|
|
|
|
Step 1: Cut up Saturated Urethane Foam |
|
|
|
|
|
Step 2: Remove Saturated urethane foam skylight |
|
|
|
|
|
Step 3: Remove Saturated urethane foam skylight |
|
|
|
|
|
Step 4: Remove Saturated urethane foam skylight |
|
|
|
|
|
Step 5: Remove Saturated urethane foam skylight |
|
|
|
|
|
Step 6: Install New 18 Gauge Metal Deck |
|
|
|
|
|
Step 7: Install new 2” Iso Insulation |
|
|
|
|
|
Step 8: Install 2 ply built-up roof as temporary waterproofing and permanent air barrier |
|
|
|
|
|
Final Step: Install new white mechanically fastened, heat welded reinforced roof membrane |
|
|
|
|
|
|
|
|
all rights reserved by acicr.com (c) 2004 webdesign and hosting by Blaze Multimedia |